Construction Updates – October

October 31st, 2019

 

Our sites have been busy this month! Keep scrolling for a snapshot of the construction progress made at our developments.

 

We have now reached practical completion and are now waiting on sign off from the powers at be. We are excited to call for settlement shortly!

 

 

 

Footings are complete across most of the development. In-ground hydraulic and electrical services are underway and garage slabs are being poured. Surveyors have set out pad and strip footing, with excavation to start soon. Dincel walls will be installed on the relevant plans following completion of slabs.

 

Kitchens and fix-out have commenced. Internal painting and fit-off is underway and roofs and roof sheeting are being laid. Roof trusses are being erected, scaffolding is up and rough-in of services has started. The team have begun internal sheeting.

 

Things have been moving quickly at Soho! Brickwork, lightweight cladding and rendering at the rear end of the buildings are now complete, as well as the eaves linings and external painting on the upper levels. Balustrade framing for the balconies plus the wet-seal for external balconies are currently underway. Pre-sheet is now 90% finished and lift void framing is complete. Scaffolding is due to be removed and excavation for the pool and lower roof covering will commence in the coming weeks.

 

October has been a busy month at Sage! Brickwork rendering is now finished, along with the lightweight cladding and rendering. Also now complete is the upper level roof with fascia, gutters, roof coverings, flashings, eaves linings and paining at the rear end of the buildings. The balconies have been poured and lift void framing is complete. Balustrade framing and wet-seal on external balconies is now underway, the team have started installing the plumbing and electrical rough-in. Scaffolding is du to be removed in the coming week.

Excavation for the pool and lower roof covering are due to commence in November. External areas including; hard and soft landscaping and verge works are set to be finalised along with finishing touches on the façade, including timber cladding and corten, will also be completed. We are excited for internal works to be finished so the final cleans can begin!